(Foundations, tailings and sedimentation ponds, leachpad design, roadways, slope stability, subsidence, ground control.)
WSMC's geotechnical experience lies in projects requiring expertise in geology, and soil/rock mechanics as they relate to foundations, tailings and sedimentation pond embankment designs, subsidence, pit slope stability, tailings pond consolidation, underground pillar/opening design, and various other projects. WSMC have access to and experience with geotechnical tools including instrumentation for stress and displacement measurements, laboratory rock and soils property testing and numerical modeling.
Project Name
|
Project Location
|
Client / Division
|
Underground Rock Mechanics Aessessment Project
|
Battle Mountain, Nevada
|
Echo Bay Minerals Company
|
WSMC made an assessment of the underground mining feasibility
of a small high grade vein in an existing pit wall. The assessment
was made primarily from a rock mechanic perspective. A review of
geologic information, and cores from the target zone was conducted
to determine preliminary rock parameters. Recommendations for rock
support, and opening designs were made based on these results. A
review of several proposed mining plans was also done for rock mechanics
compatibility. Sources of aggregate for backfill were also scoped,
and a preliminary estimate of aggregate size distribution made.
|
Project Name
|
Project Location
|
Client / Division
|
Slope Stabilization Project
|
Weber Canyon, Utah
|
Amoco Pipeline Company
|
WSMC designed and constructed a stabilization system
for slope failure that was endangering several pipelines. A geotechnical
assessment of the slope was made to determine the mechanism of slope
failure. An active resistance system using tensioned bolts and geogrid
mat was designed to stabilize the area above the failure. This would
act to protect the overlying pipeline right of way. WSMC acted as
general contractor for construction of the stabilization system.
Local subcontractors were used for labor on the project. Construction
included drilling and bolting on a very steep slope, during winter
conditions. The geogrid mat was laid and bolts tensioned, actively
clamping the soil layer to the underlying bedrock. The surface was
then seeded to US Forest Service specifications.
|
Project Name
|
Project Location
|
Client / Division
|
Pond 4 Rehabilitation
|
Sweetwater County, Wyoming
|
General Chemical Corporation
|
David H. Scriven was construction manager for the rehabilitation
of the Pond 4 embankments. The embankments were severely eroded
from wave and wind action. The assignment included determining the
physical characteristics of the fill material and measuring compaction
of replaced fill. Construction management also included making major
design changes for the upstream slope protection.
|
Project Name
|
Project Location
|
Client / Division
|
Pond 5 Enlargement
|
Sweetwater County, Wyming
|
General Chemical Corporation
|
David H. Scriven was project manager for the design
modification, permitting and construction for the enlargement of
Pond 5. The design modifications included designing a chimney drain,
realignment of the embankment, design of spillway and upstream slope
projection. Permitting included State Engineer's Permit, and construction
permits from the Wyoming Department of Environmental Quality, Water
Quality Division. Construction management included all construction
surveying, compaction testing, construction review, and development
of as-built drawings.
|
Project Name
|
Project Location
|
Client / Division
|
Tailings Cell D Modification
|
Sweetwater County, Wyoming
|
General Chemical Corporation
|
David H. Scriven was project manager and project engineer
for modification of the Tailings Disposal Cell D Reservoir. The
modification project included several phases of construction of
a retrofit on an existing tailings disposal facility using upstream
and downstream construction methods. The assignment included design,
permitting and construction management for the project. Permitting
included application for the State Engineer's Permit and Construction
Permit from the Water Quality Division, Wyoming Department of Environmental
Quality. The first phase of this project was completed in 1990,
a second phase in 1992, a third phase in 1996. The fourth phase
is scheduled for 2000 and the final phase for 2004. The designs
include a rotating multi-point discharge to facilitate the use of
sub-aerial deposition and the design of decant structures.
|
Project Name
|
Project Location
|
Client / Division
|
Railroad Design Project
|
Eagle Butte Mine
|
Amax Coal West, Inc.
|
WSMC was in charge of the design of a Loop Track Extension
and an Engine Storage Spur at the Eagle Butte Mine. The project
included surveying the existing main line track into the plant site,
design of 4800 feet of parallel track to the existing line, design
of a 400 foot spur track for engine storage, development of construction
specifications for both projects, preparation of all bid documents
and the completion of an engineering cost estimate for each project.
|
Project Name
|
Project Location
|
Client / Division
|
Mine Stability Evaluation
|
Sweetwater County, Wyoming
|
General Chemical Corporation
|
Scott P. Carlisle was the project engineer for the mine-wide
stability evaluation of the Alchem Trona Mine. The evaluation considered
mine layout, extraction, subsidence, rock strengths and in situ
stresses. Numerical models of the mine were developed to estimate
pillar stability. Areas were identified from this study for further
investigation by field testing and instrumentation to quantify pillar
conditions.
|
Project Name
|
Project Location
|
Client / Division
|
Christensen Ranch Mine
|
Casper, Wyoming
|
Cogema Mining Company
|
WSMC was the geotechnical and structural foundation
consultant in the design of a groundwater restoration facility for
Cogema Mining Company, Christensen Ranch Mine. Working closely with
Cogema process engineers a facility was designed to house the uranium
recovery columns, reverse osmosis filters, pumps and piping to be
used for cleanup of groundwater from the in-situ mine operations.
The facility was located in difficult unstable soil conditions.
WSMC was responsible for the geotechnical site investigation, piping
layout and design of a deep foundation system. The foundation design
used a deep pier foundation with slab and beam flooring to minimize
the quantity of concrete required at the remote site location.
|
Project Name
|
Project Location
|
Client / Division
|
Grouting Project
|
Spencer, South Dakota
|
Spencer Quarries Inc.
|
WSMC was asked to make an assessment of a substantial
water inflow into a quartzite quarry operated by Spencer Quarries
Inc. WSMC followed up the assessment with a design to grout off
the inflow using chemical grouting techniques. The design called
for drilling of a curtain wall and installation of sleeve port pipes
for grout injection. WSMC also acted as general contractor for construction
of the grout curtain. Denver Grouting and a local drilling contractor
were used as subcontractors for this project. Grouting of the inflow
was only partially effective. The grout curtain acted to contain
the inflow but did not stop it. WSMC provided additional designs
to excavate into the highwall along the inflow and construct an
underground bulkhead too further contain and control the inflow.
|
Project Name
|
Project Location
|
Client / Division
|
AML Projects 16-A, 16-D and 16-E-2; Gas Hills Uranium
Reclamation
|
Cheyenne, Wyoming
|
Wyoming Department of Environmenta; Quality/Land Quality
Division
|
David H. Scriven was the geotechnical consultant for
the reclamation of the John Gunnel, Veca Pit, B Pits, and Tee Pits
and a radiometric consultant for the reclamation of the B and Tee
Pits. He was responsible for the subsurface geotechnical and radiometric
investigations, the stability analyses of the highwalls and the
surface radiometric survey of the spoil piles and surrounding areas.
As part of the Design Investigation Report, he coordinated the geotechnical
testing program and performed the analysis associated with the backfill
operations of the reclamation plan and prepared radiometric isopach
maps of the spoils and areas surrounding the pits showing various
levels of radium 226 contamination.
|
Project Name
|
Project Location
|
Client / Division
|
Riley Pass Reclamation Project
|
Hardin County, South Dakota
|
Custer National Forest
|
David H. Scriven was project manager for the investigation
and design for the reclamation of the Riley Pass Uranium Mine, Hardin
County, South Dakota. He managed a team of soil scientists, geomorphologists,
biologists and health physicists to develop design alternatives
for the project. The Riley Pass Mine was a surface mine, circa late
1950's, mining uranium associated with a thin coal seam overlying
the rimrock. Spoil material was pushed over the rimrock creating
an unstable and highly erosive surface. Several highwalls were left
standing and ponded areas were created in the spoil piles. The project
included the development of several reclamation alternatives. The
alternatives were presented to the client to determine the one most
suitable to their needs. Final design and bid documents were then
prepared for the reclamation.
|
Project Name
|
Project Location
|
Client / Division
|
Surface Drainage Design and Landslide Stabilization;
Seneca No. 1 Mine Reclamation Project
|
Routt County, Colorado
|
Colorado Department of Natural Resources/Mined Land
Reclamation Division
|
Several final pits in the Seneca No. 1 Surface Coal
Mine were abandoned in the 1960's without being reclaimed. In addition,
a progressive landslide aggravated by the abandoned mine land conditions
threatened a county road, private property and a major stream course.
The reclamation design included the routing of storm runoff through
the reclaimed areas which were typically situated in steep terrain.
The construction of numerous drop structures, rip rap lined channels,
subsurface drains and compacted dikes was required. Approximately
200,000 cubic yards of earthwork was involved in the project. David
H. Scriven was staff engineer for the field investigations, analysis
and designs for stabilization of the landslide and the reclamation
of the mined-out areas and also help prepare the construction bid
documentation (drawings and specifications) and assisted the State
of Colorado in the pre-bid conferences and bid evaluation (the project
was divided into two construction contracts). Mr. Scriven was on
the project's construction management team.
|
Project Name
|
Project Location
|
Client / Division
|
Northside Mine Subsidence Study
|
Gallup, New Mexico
|
Alan K. Kuhn, Consultant and Abandoned Mine Land Bureau,
State of New Mexico
|
David H. Scriven was the subsidence investigation specialist
on the A.K. Kuhn team for the Northside Mine Subsidence Study in
Gallup, New Mexico. His assignment included interviews/workshops
with citizens; assistance to the State in locating subsurface investigation
boreholes; assistance in structure investigations; drilling supervision
and borehole logging; data analysis to define subsidence risk areas
and subsidence mechanisms; evaluations of remedial actions.
|
Project Name
|
Project Location
|
Client / Division
|
Glenrock Subsidence Control Project 8A
|
Converse County, Wyoming
|
Wyoming Department of Environmental Quality/Land Quality
Division
|
The Town of Glenrock is underlain by two abandoned underground
coal mines which are causing subsidence events on the surface. This
project included a report of investigation to determine the most
cost-effective approach to subsidence control, the design of a slurry
backfill system to pump a sand/water mixture into the mine voids
through boreholes, the generation of bid documentation and construction
specifications and the construction management of the project for
the State of Wyoming. The project also included design and construction
management of an extensive grouting program for protection of structures
and roadways in subsidence-prone areas where hydraulic backfilling
would not be effective. The grouting applications follow:
- Development of grouted gravel columns, through boreholes,
in the mains to contain the slurry backfill.
- Development of a cement-fly ash grout curtain around
the perimeter of an apartment complex to contain weak backstow material
in the underlying mine workings.
- Development and execution of a grouting program utilizing
various drilling equipment and procedures and various grout mixtures
to stabilize developed commercial and residential properties, streets
and utilities that were threatened by subsidence.
- Stabilization of 1200 feet of State Highway 20-25 that
was undermined and a very high subsidence risk.
|
Project Name
|
Project Location
|
Client / Division
|
Superior AML Project 6B
|
Sweetwater County, Wyoming
|
Wyoming Department of Environmental Quality/Land Quality
Division
|
The Town of Superior is located in a major turn-of-the-century
coal mining district in southwestern Wyoming. Several hazards to
the public associated with the abandoned underground coal mines
had to be addressed. Our work included the following investigations,
design, development of construction documents and construction management:
- Subsidence control by grouting beneath commercial structures
and an undermined public school. A specialized grouting technique
and grout mixture were used beneath the school because of the nature
of the trough-type rock collapse and the weakened soils. The ground
improvement involved the use of Tube-a-Manchette grout casing which
allows for considerable control of the "zone" in which the grout
is injected. The cement-fly ash grout base was designed for the
special ground and injection conditions by incorporation of admixtures
for strength (silica fume), fluidity and plasticity (polyethylene
glycol), and set retardant (sugar).
- Closures for 32 abandoned coal mine openings (exposed
adits and inclines, sink holes into mine workings).
- Reclamation of four coal waste areas.
- Closure of a concrete lined ventilation shaft.
|
Project Name
|
Project Location
|
Client / Division
|
Geotechnical, Hydrological and Mining Engineering Support
|
Clear Creek/Central City Site RI/FS
|
Camp Dresser & McKee Inc. (CDM)
|
D.H. Scriven was staff engineer for the geotechnical
subcontractor to CDM on the Remedial Investigation/Feasibility Study
at five Superfund sites in Clear Creek and Gilpin Counties, Colorado.
The sites included mine waste rock and tailings dumps, several adjacent
to perennial streams. Mr. Scriven performed subsurface investigations
(borehole drilling and sampling), piezometer installations, sample
selection for physical testing, analysis of laboratory results and
slope stability analysis. Stable configurations were determined
and alternative remedial methods were evaluated. A comprehensive
geotechnical report was prepared in support of and complementary
to CDM's RI/FS efforts.
|
Project Name
|
Project Location
|
Client / Division
|
Tailings Pond 4 Modification
|
Rhone-Poulenc of Wyoming Company; Big Island Mine
|
Jacobs Engineering Group
|
WSMC provided tailings dam design expertise to Jacobs
Engineering for the Debottlenecking Project at the Rhone Poulenc
of Wyoming Company Big Island Mine. We designed, permitted and provided
construction review for the modification of Pond 4 to construct
an interior tailings deposition area. The project included construction
of two tailings cells each with decant tower and discharge pipe
and embankments utilizing both upstream and downstream construction
methods. The assignment included identification and testing of suitable
borrow materials from within the already disturbed areas.
|
Project Name
|
Project Location
|
Client / Division
|
Pond 1 Modification
|
Green River, Wyoming
|
Tenneco Soda Ash Company
|
WSMC provided design and permitting services for Tenneco
Soda Ash Company to modify their evaporation pond and increase its
storage capacity. The assignment included design of two auxiliary
embankments with cementacious grout curtains for seepage control,
a five to six foot downstream raise of the main embankment including
installation of a chimney drain, and the design of two interceptor
trenches and pumpback system. The modification constructed during
the summer of 1992, added approximately 1300 acre feet of storage
capacity to the facility. Project also included installation of
eight monitor wells around the perimeter of the facility and five
piezometer wells in the embankment.
|
Project Name
|
Project Location
|
Client / Division
|
Laboratory Rock Mechanics Testing
|
Meeker, Colorado
|
Kennecott Colowyo Coal Company
|
Scott P. Carlisle was the project engineer on a rock
mechanics laboratory investigation for a potential underground coal
mine. Tests conducted were unconfined compressive strengths, triaxial
strengths, brazil tensile strength, bulk density, porosity, and
slake durability. Data from the seam, roof, and floor were collected
and reduced to establish rock properties for mine development and
longwall design.
|
Project Name
|
Project Location
|
Client / Division
|
Rock Bolt Field Testing
|
Sweetwater County, Wyoming
|
Rhone-Poulenc-Big Island Mine
|
Scott P. Carlisle was the project engineer on a rock
bolt evaluation program. The program evaluated different anchor
horizons, and rock anchors with respect to the two beds in the mine.
This work included rock bolt pull testing, torque testing, borescoping,
and statistical analysis of the results. The results were given
to the operator for consideration of changes in the rock support
used at the mine.
|
Project Name
|
Project Location
|
Client / Division
|
Field Instrmentation; Yucca Mountain Tunnel Project
|
Las Vegas, Nevada
|
N/A
|
Scott P. Carlisle was the project engineer for an extensive
tunnel instrumentation project. This work included instrumentation
selection and installation to achieve construction monitoring goals
required by nuclear facility regulators. It also included selection
and installation of data acquisition systems to facilitate instrument
reading. Instrumentation included stress monitoring gages, convergence
stations, borehole extensometers, rock bolt load cells, instrumented
rock bolts, and steel set strain gages. Other aspects of the project
included blast vibration monitoring for blast evaluation, and structural
response to blasting and tunnel rock quality estimation for ground
support selection.
|
Project Name
|
Project Location
|
Client / Division
|
Subsidence Analysis
|
Hazard County, Kentucky
|
Whitaker Coal Company
|
Scott P. Carlisle was the senior engineer on a subsidence
evaluation for a proposed underground coal mine. The mine was to
be located under existing structures including residential buildings,
power lines, gas wells and pipe lines. Estimates were made regarding
stresses and displacements to these structures due to mine subsidence.
Recommendations for protection of structures from subsidence were
also included. This work was included as part of an overall mine
feasibility project.
|
Project Name
|
Project Location
|
Client / Division
|
Tunnel Design and Construction
|
Trementina, New Mexico
|
International Ground Support Systems
|
Scott P. Carlisle was the project engineer and construction
superintendent for an underground records storage facility. This
project included design and excavation of a shotcrete lined tunnel,
installation of ventilation, lighting, and security, and design
and construction of surface facilities. A preliminary design and
site evaluation for a second facility using cut and cover tunnel
techniques was also conducted for the client.
|
Project Name
|
Project Location
|
Client / Division
|
Rock Mechanics
|
Lucky Friday and Star Mines
|
Hecla Mining Co.
|
Scott P. Carlisle was the rock mechanics engineer for
these mines. Projects included rock support and opening design for
high stress conditions, stope sequencing using numerical modeling,
microseismic system design and installation, rock burst monitoring,
and smooth wall blast design.
|
Project Name
|
Project Location
|
Client / Division
|
Pond 3 North Embankment Dewatering Project
|
Green River, Wyoming
|
Texas-Gulf Soda Ash
|
Mike C. Hawks was the project hydrogeologist obtaining
geologic and hydrologic data for the design of a dewatering/pumpback
wellfield system for capture of seepage from Tailings Pond #3. The
seepage was causing damage to local flora and creating areas of
standing water near the toe of the dike impeding heavy equipment
access for a proposed 8 ft lift on the dike. An extensive drilling
and coring program coupled with aquifer pump tests was conducted
to evaluate subsurface geologic conditions and aquifer properties.
The dewatering/pumpback system dewatered the surface seeps allowing
for pond expansion and increased soda ash production.
|
Project Name
|
Project Location
|
Client / Division
|
Groundwater Restoration Facility Design; Coal Blending
Conveyor Project
|
Glenrock, Wyoming
|
Glenrock Coal Company
|
WSMC was the design firm for the coal blending conveyor
project for Glenrock Coal Company. The project included site layout
and engineering for a feeder breaker, transfer conveyor and stockpile
system to be used for blending pit run coal. A geotechnical investigation
was conducted for the component sites. Designs were developed for
the foundations of the feeder breaker and conveyor towers. Dump
and stockpile retaining walls and a transfer tunnel escapeway were
also included in the design package. Design drawings, technical
specifications, and a bid package was prepared for purchase of the
conveyor and for site construction and erection of the conveyor.
|
|